When should I use this guide?
When you want to divide the project into stages, for example Site setup or Frame part 1.
When you want to change the name or dates of an activity.
When you want to remove, restore or delete an activity.
Requirements
You are a member of the project.
Activities is enabled for the project. This is the default for new projects.
How to do it
An activity is a stage in the project with a name and a start and end date. Only the name is required.
On the web
Open the activities
Go to Places and open the project.
Click the Open in App icon next to the project name. The project view opens in your browser, not in the mobile app.
Click Activities in the side menu below the project name.
The Activities page has the Active and Removed tabs. Click the arrow on the left of a row to see the equipment in the activity.
Create an activity
Click Create new at the top right of the Active tab.
Fill in Name.
Select dates in Start and Stop.
Click Create.
Edit an activity
You can change the start and end dates directly in the list. To change the name:
Click the three-dot menu on the row and select Edit.
Change Name, Start or Stop.
Click Save.
Remove, restore and delete
Click the three-dot menu on the row and select Remove.
Confirm with Remove.
The activity is moved to the Removed tab. There you can click the three-dot menu and select:
Restore to move the activity back to Active.
Delete (permanent) to delete the activity. This cannot be undone.
Confirm your choice in the dialog.
In the app
Open the activities
Open the project.
Tap Activities in the bottom menu.
On the Active tab, activities are shown under Current and Coming. Activities that have finished are shown under Ended.
Create an activity
Tap the round + button at the bottom right.
Fill in Name of activity.
Select Start and End under Dates.
Tap Create activity.
Edit an activity
Tap the pencil on the activity's row. The Edit tab opens.
Change the name or dates and tap Save.
If you tap the activity itself, the Items tab shows the equipment in the activity and Cost of activity, split into To date and Remaining.
Remove, restore and delete
Tap the pencil on the activity's row.
Tap Remove.
The activity is moved to the Removed tab. There you can:
restore it: tap the three dots on the row and select Restore.
delete it permanently: tap the activity, open the Edit tab and tap Delete. This cannot be undone. Confirm with Delete in the Delete activity? dialog.
If it does not work
First, check that:
you are a member of the project,
the activity has a name,
the end date is not before the start date.
If Activities is missing from the project menu
Activities is not enabled for the project. Contact Infobric.
If an activity is missing from the list
Check the Removed tab. A removed activity can be restored from there.
Tips!
Give activities names that everyone in the project recognizes, for example Site setup or Frame part 1.
Remove an activity instead of deleting it permanently if you might need it again.
With activities, you can also plan equipment per stage and import activities from Excel. This is described in separate guides.