Common uses
Divide the project into stages with start and end dates, for example Site setup or Frame part 1.
Plan how long equipment is needed, so that the return date follows the project's stages.
Follow the cost of equipment per stage.
Import the project schedule from Excel instead of creating each activity manually.
Requirements
You are a member of the project.
Activities is enabled for the project. This is the default for new projects.
Get started
On the web
Go to Places and open the project.
Click the Open in App icon next to the project name. The project view opens in your browser, not in the mobile app.
Click Activities in the side menu below the project name.
In the app
Tap Places in the bottom menu and open the project.
Tap Activities in the bottom menu.
What you can do with activities
Create and manage activities
An activity is a stage in the project with a name and a start and end date. Only the name is required.
On the web, the Activities page has the Active, Removed and Upload tabs. You create a new activity with Create new. Click the arrow on the left of a row to see the equipment in the activity.
In the app, the Activities page has the Active and Removed tabs. Activities are shown under Current, Coming and Ended. You create a new activity with the round + button.
An activity that you remove ends up under Removed. There you can restore it or delete it permanently.
How to create, edit, remove and restore activities is described in the guide Create and manage activities.
Plan equipment and return dates
You plan equipment by adding it to one or more activities. The estimated return date then becomes the end date of the last activity and is shown as From last activity followed by the activity's name. If you set your own date on the equipment, that date applies instead.
You can plan several items at once via Manage selected on the web and Manage in the app.
How to do this is described in the guide Plan equipment with activities.
Follow the cost per activity
On the web, the list of activities shows Name, Start, Stop, Items, Calculated total cost and Cost per workday for each activity.
In the app, tap an activity. The Items tab shows the equipment in the activity and Cost of activity, split into To date and Remaining.
Import activities from Excel
On the web, you can import many activities at once from an Excel file (.xlsx) on the Upload tab. Download the Excel template, fill in one row per activity and upload the file. If a row has the same name as an activity that already exists, its dates are updated.
How to do this is described in the guide Import activities from Excel.
Tips!
Give activities names that everyone in the project recognizes, and use the same names when you import again.
Add the equipment to every activity where it is needed. The return date follows the last activity.
Click an activity's name on the web to see the equipment in the activity in the equipment list.
Is Activities missing from the project menu? Then Activities is not enabled for the project. Contact Infobric.